Construction of Balbagon Seawall including Wave Breaker, Mambajao, Camiguin
Location
Balbagon, Mambajao, Camiguin
Northern Mindanao
ZIP: 9100
9.248222, 124.731915
Project Cost
₱48M
₱47,527,222.7
Project Timeline
Start Date
April 26, 2023
Wed, Apr 26, 2023
Actual Start
April 26, 2023
Wed, Apr 26, 2023
Target Completion
August 31, 2024
Sat, Aug 31, 2024
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor