Construction of Flood Control Project (Roa Crusher) along Upper Balulang Section 1, Cagayan de Oro City
Location
Balulang, City of Cagayan De Oro, Misamis Oriental
Northern Mindanao
ZIP: 9000
8.423679, 124.630068
Project Cost
₱66M
₱66,022,344.63
Project Timeline
Start Date
February 12, 2023
Sun, Feb 12, 2023
Actual Start
February 12, 2023
Sun, Feb 12, 2023
Target Completion
July 30, 2024
Tue, Jul 30, 2024
Project Location Map
Location Map
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor