Construction of Riverwall (Phase 2), Barangay Dampalit, Malabon City
Location
Dampalit, City of Malabon
NCR
ZIP: 1480
14.701498, 120.927658
Project Cost
₱50M
₱49,500,000.0
Project Timeline
Start Date
February 14, 2022
Mon, Feb 14, 2022
Actual Start
February 14, 2022
Mon, Feb 14, 2022
Target Completion
January 26, 2023
Thu, Jan 26, 2023
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close
Loading comments...