Construction of Barit River Flood Mitigation Structure (Antipolo Young Section), Nabua, Camarines Sur
Location
Antipolo Young, Nabua, Camarines Sur
Bicol Region
ZIP: 4434
13.403187, 123.379533
Project Cost
₱93M
₱93,127,727.21
Project Timeline
Start Date
March 20, 2022
Sun, Mar 20, 2022
Actual Start
March 20, 2022
Sun, Mar 20, 2022
Target Completion
November 29, 2022
Tue, Nov 29, 2022
Project Location Map
Location Map
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor