Government Contractor Profile & Statistics
Total Projects
6
Total Value
₱310M
₱311,141,703.11
Avg. Cost
₱52M
Avg. Progress
N/A
Project Status Distribution
Completed
6 projects
(100.0%)
Contract Value by Status
Completed
₱310M
₱311,141,703.11
Yearly Statistics
| Year | Projects | Total Value | Average Cost |
|---|---|---|---|
| 2024 | 1 |
₱68M ₱67,547,177.24 |
₱68M |
| 2023 | 1 |
₱49M ₱48,997,251.2 |
₱49M |
| 2022 | 4 |
₱190M ₱194,597,274.67 |
₱49M |
Projects by Region
MIMAROPA Region
6 projects₱310M
₱311,141,703.11
Top 10 Provinces
1
6
Oriental Mindoro
₱310M
₱311,141,703.11
Top 10 Projects by Contract Value
1
Construction of Bansud River Control, Sta. 6+909 - Sta. 7+340 (Upstream - Right Side), Barangay Conrazon, Bansud, Oriental Mindoro
P00821355LZ
Completed
Conrazon, Bansud, Oriental Mindoro
₱68M
₱67,547,177.24
2
Construction of Flood Mitigating Structure along Mag-Asawang Tubig River, Sta. 0+000 - Sta. 0+242 U/S, Sta. 0+000 - Sta. 0+123 D/S, San Andres Putik, Naujan, Oriental Mindoro
P00621112LZ
Completed
San Andres, Naujan, Oriental Mindoro
₱49M
₱48,999,957.5
3
Construction of Malitbog River Control Structure (Downstream), Bongabong, Oriental Mindoro
P00639533LZ
Completed
Bongabong, Oriental Mindoro
₱49M
₱48,999,912.4
4
Construction of Baroc River Control, Brgy. San Miguel Section, Sta. 0+000 - Sta. 0+802, Roxas, Oriental Mindoro
P00621118LZ
Completed
San Miguel, Roxas, Oriental Mindoro
₱49M
₱48,999,910.68
5
Construction of Pula River Control Structure, Barangay Santa Maria Section, Pinamalayan, Oriental Mindoro
P00726771LZ
Completed
Pinamalayan, Oriental Mindoro
₱49M
₱48,997,251.2
6
Construction of Baroc River Control, Villa Celestial Section, Sta. 0+000 - Sta. 0+680, Mansalay, Oriental Mindoro
P00621120LZ
Completed
Villa Celestial, Mansalay, Oriental Mindoro
₱48M
₱47,597,494.09
Projects by Type
Main Portal
6 projects
₱310M