Construction of Malitbog River Control Structure (Downstream), Bongabong, Oriental Mindoro
Location
Bongabong, Oriental Mindoro
MIMAROPA Region
ZIP: 5211
12.758889, 121.469167
Project Cost
₱49M
₱48,999,912.4
Project Timeline
Start Date
April 10, 2022
Sun, Apr 10, 2022
Actual Start
April 10, 2022
Sun, Apr 10, 2022
Target Completion
February 13, 2023
Mon, Feb 13, 2023
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close