Infrastructure Projects

Explore government infrastructure projects across the Philippines with complete transparency

Track progress, funding, contractors, and locations. Building a more informed and accountable Philippines, together.

Active Filters

Clear All
Total Projects
9,818
Total Cost
₱420B
₱417,659,277,654.8
Current Page
407 of 491
20 per page
Flood Control Infrastructure Main Portal

Construction of Vinisitahan Flood Control (Downstream) along Baclayon River, Bacacay, Albay

P00727207LZ Completed
Location
Bacacay, Albay
Cost
₱25M
Start
May 08, 2023
Completion
Sep 14, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
JELSIE CONSTRUCTION & SUPPLY
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Flood Mitigation Structure/Shoreline Protection, Barangay Macabari, Barcelona, Sorsogon

P00737575LZ Completed
Location
Macabari, Barcelona, Sorsogon
Cost
₱20M
Start
May 01, 2023
Completion
Oct 28, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
ARDA CONSTRUCTION AND SUPPLY
Tap to view details
Flood Control Infrastructure Main Portal

Construction/ Improvement of Slope Protection along Roy Padilla Highway, San Lorenzo Ruiz, Camarines Norte

P00620304LZ Completed
Location
San Lorenzo Ruiz, Camarines Norte
Cost
₱87M
Start
Jul 13, 2022
Completion
Dec 25, 2023
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
EUS CONSTRUCTION / 128 DRAGON CONSTRUCTION AND SUPPLIES
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Flood Control Structure (Phase 2) at Brgy. Mabilo, Labo, Camarines Norte

P00631390LZ Completed
Location
Labo, Camarines Norte
Cost
₱34M
Start
Mar 20, 2022
Completion
May 03, 2023
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
EOZ CONSTRUCTION
Tap to view details
Flood Control Infrastructure Main Portal

Construction of River Control, Barangay Mabilo I - Barangay San Antonio, Labo, Camarines Norte

P00631411LZ Completed
Location
Mabilo I, Labo, Camarines Norte
Cost
₱49M
Start
Mar 16, 2022
Completion
Nov 24, 2022
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
BRENTMIN ROOFING ENTERPRISE
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Flood Mitigation Structure, Camaligan, Camarines Sur

P00620724LZ Completed
Location
Camaligan, Camarines Sur
Cost
₱43M
Start
Mar 23, 2022
Completion
Oct 04, 2022
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
CRJ CONST AND DEVELOPMENT INC
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Flood Control Structure at Brgy. Mabilo 1, Labo, Camarines Norte

P00631394LZ Completed
Location
Labo, Camarines Norte
Cost
₱33M
Start
Mar 20, 2022
Completion
Mar 02, 2023
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
BRENTMIN ROOFING ENTERPRISE
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Flood Control Structure (Phase 1) at Brgy. Mabilo, Labo, Camarines Norte

P00631389LZ Completed
Location
Labo, Camarines Norte
Cost
₱33M
Start
Mar 20, 2022
Completion
Mar 02, 2023
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
BRENTMIN ROOFING ENTERPRISE
Tap to view details
Flood Control Infrastructure Main Portal

Construction/Improvement of Labo River Flood Mitigation Structure, Brgy. Bakiad, Labo, Camarines Norte

P00620318LZ Completed
Location
Bakiad, Labo, Camarines Norte
Cost
₱130M
Start
Mar 23, 2022
Completion
May 31, 2023
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
HGG BUILDERS & SUPPLY
Tap to view details
Flood Control Infrastructure Main Portal

Construction/Rehabilitation/Improvement of Flood Mitigation Structure, Bicol River Flood Control, Brgy. Tabuco (Tabuco Section - Left Side), Naga City

P00621548LZ Completed
Location
Tabuco, City of Naga, Camarines Sur
Cost
₱39M
Start
Apr 05, 2022
Completion
Nov 10, 2022
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
CPR CONSTRUCTION AND SUPPLY, INC. (FORMERLY: CPR CONSTRUCTION AND SUPPLY) / 417 LP CONSTRUCTION CORPORATION
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Revetment (along Bicol River) within Bicol River Basin, Brgy. Alimbuyog, Milaor, Camarines Sur

P00620716LZ Completed
Location
Alimbuyog, Milaor, Camarines Sur
Cost
₱48M
Start
Feb 21, 2022
Completion
Sep 13, 2022
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
KEASCIA CONSTRUCTION & SUPPLY
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Labo River Control (Singi Section) Barangay Singi, Vinzons, Camarines Norte

P00631406LZ Completed
Location
Singi, Vinzons, Camarines Norte
Cost
₱41M
Start
Mar 22, 2022
Completion
Nov 22, 2022
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
BRENTMIN ROOFING ENTERPRISE
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Flood Control Structure, Brgy. Dagotdotan, San Lorenzo Ruiz, Camarines Norte

P00640467LZ Completed
Location
Dagotdotan, San Lorenzo Ruiz, Camarines Norte
Cost
₱99M
Start
Mar 30, 2022
Completion
Apr 29, 2023
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
EOZ CONSTRUCTION
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Dike (along Bicol River) within Bicol River Basin, Brgy. Bagongbong, Minalabac, Camarines Sur

P00620700LZ Completed
Location
Bagongbong, Minalabac, Camarines Sur
Cost
₱48M
Start
Feb 27, 2022
Completion
Sep 19, 2022
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
HI-TONE CONSTRUCTION & DEVELOPMENT CORP. (FORMERLY
Tap to view details
Flood Control Infrastructure Main Portal

Construction/Rehabilitation/Improvement of Flood Mitigation Structure, Calabanga Flood Control, Brgy. Sabang-Salvacion Baybay- San Roque-San Pablo, Calabanga, Camarines Sur (Both Sides)

P00621549LZ Completed
Location
Sabang, Calabanga, Camarines Sur
Cost
₱49M
Start
Apr 03, 2022
Completion
Oct 26, 2022
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
PEU CONSTRUCTION AND SUPPLY / STEVEN CONSTRUCTION & SUPPLY
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Flood Clontrol Structure, Barangay San Antonio, San Lorenzo Ruiz (Phase II), Camarines Norte

P00640466LZ Completed
Location
San Antonio, San Lorenzo Ruiz, Camarines Norte
Cost
₱99M
Start
Mar 24, 2022
Completion
Aug 11, 2022
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
EUS CONSTRUCTION / BRENTMIN ROOFING ENTERPRISE
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Daet River Control Structure, Brgy. 1 Section Barangay 1, Daet, Camarines Norte

P00621485LZ Completed
Location
Daet, Camarines Norte
Cost
₱29M
Start
Mar 29, 2022
Completion
Sep 16, 2022
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
EOZ CONSTRUCTION
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Sula Seawall, Barangay Sula, Vinzons, Camarines Norte

P00630991LZ Completed
Location
Sula, Vinzons, Camarines Norte
Cost
₱49M
Start
Mar 21, 2022
Completion
Jan 27, 2023
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
BRENTMIN ROOFING ENTERPRISE
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Protection Works, Barangay Dogongan, Daet, Camarines Norte

P00621484LZ Completed
Location
Dogongan, Daet, Camarines Norte
Cost
₱29M
Start
Mar 30, 2022
Completion
Oct 17, 2022
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
888RV CONSTRUCTION AND SUPPLIES
Tap to view details
Flood Control Infrastructure Main Portal

Improvement of Flood Mitigation Structure along Himoragat River, Tinambac, Camarines Sur

P00631427LZ Completed
Location
Tinambac, Camarines Sur
Cost
₱29M
Start
Feb 14, 2022
Completion
Jul 12, 2023
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
SAMARAH CONSTRUCTION AND SUPPLY
Tap to view details

Data Source

Powered by official government infrastructure monitoring data

Project DIME

Digital Imaging for Monitoring and Evaluation

A digital transformation initiative by the Department of Budget and Management (DBM) in partnership with the Philippine Open Government Partnership, relaunched in 2023 to enable participatory and real-time monitoring of government infrastructure projects.

How It Works

Advanced Monitoring: Uses satellites, drones, and geotagging technologies to track high-value infrastructure projects nationwide

Citizen Participation: Empowers Filipinos to monitor project progress and provide feedback on actual project status

Enhanced Transparency: Ensures public funds are used effectively through open data and real-time project monitoring

Mission

Provide an efficient mechanism for monitoring and evaluation of government programs through innovative use of technologies

Vision

Integrate science-based monitoring and evaluation principles into the government's budget and management system

"Project DIME is a game-changer—ensuring greater efficiency, transparency, and public participation in the way services are delivered to the Filipino people."

Secretary Amenah F. Pangandaman

DBM Secretary

Learn more about Project DIME
Visit Official Site