Flood Control Infrastructure Main Portal

Rehabilitation of Pampanga River Flood Control, Brgy. Sto. Tomas North, Jaen, Nueva Ecija, Sta. 42 + 300.40 to Sta. 42 + 564.40

P00644777LZ Completed
Location
Jaen, Nueva Ecija
Cost
₱17M
Start
Mar 19, 2023
Completion
Aug 29, 2023
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
F-DEY CONSTRUCTION AND TRADING
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Pampanga River Control, Sta. 0+000 - Sta. 0+520, Brgy. San Anton, San Leonardo, Nueva Ecija

P00620840LZ Completed
Location
San Anton, San Leonardo, Nueva Ecija
Cost
₱74M
Start
Mar 01, 2022
Completion
Nov 26, 2022
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
FRAMECON BUILDERS
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Slope Protection along Balagtas River, Sta. 01 + 947 to Sta. 02 + 237, San Juan Section, Balagtas, Bulacan

P00621280LZ Completed
Location
San Juan, Balagtas, Bulacan
Cost
₱68M
Start
Apr 03, 2022
Completion
Dec 28, 2022
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
DMLC BUILDERS
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Drainage Canal along Barangays Subic, Tibag and Sabang, Baliuag, Bulacan

P00632811LZ Completed
Location
Subic, Baliuag, Bulacan
Cost
₱20M
Start
Feb 13, 2022
Completion
Oct 10, 2022
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
WBX CONSTRUCTION, INC (FORMERLY WBX CONSTRUCTION)
Tap to view details
Flood Control Infrastructure Main Portal

Rehabilitation of River Control Structures, Sta. Cruz (Bagbag Creek), Guiguinto, Bulacan

P00631219LZ Completed
Location
Guiguinto, Bulacan
Cost
₱45M
Start
Mar 03, 2022
Completion
Nov 20, 2022
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
TOPNOTCH CATALYST BUILDERS INC. / BLACK HARDHAT INC. (FORMERLY: JCHARDHAT INC.)
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Riverbank Protection along Balagtas River Brgy. Santol, Balagtas, Bulacan

P00639350LZ Completed
Location
Santol, Balagtas, Bulacan
Cost
₱58M
Start
Apr 03, 2022
Completion
Feb 26, 2023
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
729 CONSTRUCTION, INC. (FORMERLY 722 CONSTRUCTION, INC.)
Tap to view details
Flood Control Infrastructure Main Portal

Construction of River Protection, Balubad, Bulacan, Bulacan

P00631204LZ Completed
Location
Balubad, Bulacan, Bulacan
Cost
₱35M
Start
Jan 27, 2022
Completion
Jul 25, 2022
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
J. SIMEON CONSTRUCTION
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Flood Control Structures along Balagtas River, Sta. 0 + 475 - Sta. 0 + 829, Barangay Panginay, Balagtas, Bulacan

P00620518LZ Completed
Location
Panginay, Balagtas, Bulacan
Cost
₱47M
Start
Jan 27, 2022
Completion
Sep 23, 2022
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
M.C.J. VALENZUELA CONSTRUCTION ENTERPRISES
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Flood Control Structure along Bulo River, Sta. 12+700 - Sta. 13+000, San Miguel, Bulacan

P00621277LZ Completed
Location
Poblacion, San Miguel, Bulacan
Cost
₱61M
Start
Mar 29, 2022
Completion
Feb 27, 2023
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
L.R. TIQUI BUILDERS, INC.
Tap to view details
Flood Control Infrastructure Main Portal

Rehabilitation of Flood Control Structure along Angat River, Parulan Section, Sta. 0 + 000 to Sta. 0 + 353.60, Plaridel, Bulacan

P00621076LZ Completed
Location
Parulan, Plaridel, Bulacan
Cost
₱49M
Start
Feb 17, 2022
Completion
May 12, 2023
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
TOPNOTCH CATALYST BUILDERS INC.
Tap to view details
Flood Control Infrastructure Main Portal

Rehabilitation of Flood Structure along Barangay Pinagbarilan, Baliwag, Bulacan

P00621450LZ Completed
Location
Pinagbarilan, Baliuag, Bulacan
Cost
₱4.9M
Start
Apr 05, 2022
Completion
Jun 30, 2022
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
ISOBEL CONCRETE CONSTRUCTOR CORPORATION
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Flood Control Wall, Poblacion, Guiguinto, Bulacan, Sta. 0+157-Sta.0+301

P00631192LZ Completed
Location
Poblacion, Guiguinto, Bulacan
Cost
₱23M
Start
Apr 05, 2022
Completion
Jul 21, 2022
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
F.R. MAPILISAN CONSTRUCTION
Tap to view details
Flood Control Infrastructure Main Portal

Improvement of Waterways with Flood Control Structures along Balagtas River, Sta. 0 + 000 to Sta. 0 + 540, Wawa, Balagtas, Bulacan

P00630944LZ Completed
Location
Balagtas, Bulacan
Cost
₱63M
Start
Feb 23, 2022
Completion
Nov 19, 2022
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
L.R. TIQUI BUILDERS, INC.
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Flood Mitigation Structure at Malayop Creek, Barangay Ilog Baliwag, Quezon, Nueva Ecija

P00632833LZ Completed
Location
Ilog Baliwag, Quezon, Nueva Ecija
Cost
₱11M
Start
Feb 16, 2022
Completion
Dec 11, 2022
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
R.A. PAHATI CONST. & SUPPLY, INC.
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Slope Protection Structures at Guiguinto River (Bagbag Creek, Sta. 0 + 000 - Sta. 0 + 780), Barangay Malis, Guiguinto, Bulacan

P00631211LZ Completed
Location
Malis, Guiguinto, Bulacan
Cost
₱45M
Start
Jan 27, 2022
Completion
Oct 23, 2022
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
ANORE CONSTRUCTION
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Flood Control Structures along Guiguinto River Sta. 01+840 to Sta. 02+040 Malis Section, Guiguinto, Bulacan

P00621531LZ Completed
Location
Malis, Guiguinto, Bulacan
Cost
₱24M
Start
Apr 04, 2022
Completion
Dec 26, 2022
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
N.M.E. CONSTRUCTION
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Flood Control Structure and Improvement of Waterways at Brgy. Hinukay, Baliuag, Bulacan

P00639467LZ Completed
Location
Hinukay, Baliuag, Bulacan
Cost
₱49M
Start
Apr 04, 2022
Completion
Dec 06, 2022
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
ST. MATTHEW GEN. CONTRACTOR & DEVELOPMENT CORP.
Tap to view details
Flood Control Infrastructure Main Portal

Rehabilitation of River Protection Structure along Bulusan, Calumpit, Bulacan

P00630945LZ Completed
Location
Bulusan, Calumpit, Bulacan
Cost
₱96M
Start
Feb 17, 2022
Completion
Feb 11, 2023
Fund Source
General Appropriations Act FY 2022
Agencies
DPWH
Contractor
ST. TIMOTHY CONSTRUCTION CORPORATION
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Drainage Structure, Lumban, Tangub City, Misamis Occidental

P00835872MN Completed
Location
Lumban, City of Tangub, Misamis Occidental
Cost
₱4.8M
Start
Jun 19, 2024
Completion
Jan 27, 2025
Fund Source
General Appropriations Act FY 2024
Agencies
DPWH
Contractor
WILKINSON CONSTRUCTION
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Dinas Drainage Structure, Sinacaban, Misamis Occidental

P00835870MN Completed
Location
Sinacaban, Misamis Occidental
Cost
₱4.8M
Start
Jun 19, 2024
Completion
Nov 24, 2024
Fund Source
General Appropriations Act FY 2024
Agencies
DPWH
Contractor
WILKINSON CONSTRUCTION
Tap to view details

Data Source

Powered by official government infrastructure monitoring data

Project DIME

Digital Imaging for Monitoring and Evaluation

A digital transformation initiative by the Department of Budget and Management (DBM) in partnership with the Philippine Open Government Partnership, relaunched in 2023 to enable participatory and real-time monitoring of government infrastructure projects.

How It Works

Advanced Monitoring: Uses satellites, drones, and geotagging technologies to track high-value infrastructure projects nationwide

Citizen Participation: Empowers Filipinos to monitor project progress and provide feedback on actual project status

Enhanced Transparency: Ensures public funds are used effectively through open data and real-time project monitoring

Mission

Provide an efficient mechanism for monitoring and evaluation of government programs through innovative use of technologies

Vision

Integrate science-based monitoring and evaluation principles into the government's budget and management system

"Project DIME is a game-changer—ensuring greater efficiency, transparency, and public participation in the way services are delivered to the Filipino people."

Secretary Amenah F. Pangandaman

DBM Secretary

Learn more about Project DIME
Visit Official Site