Infrastructure Projects

Explore government infrastructure projects across the Philippines with complete transparency

Track progress, funding, contractors, and locations. Building a more informed and accountable Philippines, together.

Active Filters

Clear All
Total Projects
9,818
Total Cost
₱420B
₱417,659,277,654.8
Current Page
266 of 491
20 per page
Flood Control Infrastructure Main Portal

Construction of Bank Protection Structures along Brgy. Mindanao - Brgy. Sorsogon, Malabuyoc, Cebu

P00721908VS Completed
Location
Mindanao, Malabuyoc, Cebu
Cost
₱72M
Start
Mar 15, 2023
Completion
Nov 23, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
L.C. CONSTRUCTION CORPORATION (FOR: L.C. CONSTRUCTION)
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Revetment Wall along Matutinao River (Upstream), Badian, Cebu

P00721512VS Completed
Location
Tubod, Badian, Cebu
Cost
₱96M
Start
Feb 07, 2023
Completion
Dec 17, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
WTG CONSTRUCTION & DEVELOPMENT CORPORATION
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Revetment Wall at Barangay Tupas - Barangay Vive River Flood Control, Ronda, Cebu

P00733241VS Completed
Location
Tupas, Ronda, Cebu
Cost
₱96M
Start
Apr 10, 2023
Completion
Dec 18, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
WTG CONSTRUCTION & DEVELOPMENT CORPORATION
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Storm Surge Protection Structures at Sitio Kalubihan, Barangay Guiwanon, Ginatilan, Cebu (Package 2)

P00733261VS Completed
Location
Guiwanon, Ginatilan, Cebu
Cost
₱96M
Start
Apr 10, 2023
Completion
Dec 10, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
QM BUILDERS
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Tamogong River Control, Bais City, Negros Oriental

P00731632VS Completed
Location
Tamogong, City of Bais, Negros Oriental
Cost
₱97M
Start
Mar 09, 2023
Completion
Feb 11, 2024
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
PHILSOUTH BUILDERS INC (FORMERLY:PHILSOUTH BUILDERS)
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Bayawan River Control, Upstream, Bayawan City, Negros Oriental, Phase II

P00722002VS Completed
Location
City of Bayawan, Negros Oriental
Cost
₱49M
Start
Apr 18, 2023
Completion
Dec 14, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
LEGACY CONSTRUCTION CORPORATION (FORMERLY: LEGACY CONSTRUCTION) / MIGHTY HOK SUMMIT CONSTRUCTION & DEVELOPMENT CORP.
Tap to view details
Flood Control Infrastructure Main Portal

Rehabilitation of Tanjay River Control, Pamplona Section, Simborio, Pamplona, Negros Oriental

P00721843VS Completed
Location
Simborio, Pamplona, Negros Oriental
Cost
₱49M
Start
Feb 05, 2023
Completion
Nov 25, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
PHILSOUTH BUILDERS INC (FORMERLY:PHILSOUTH BUILDERS)
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Groundsill along Saliring River (Upstream), Malabuyoc, Cebu

P00733272VS Completed
Location
Malabuyoc, Cebu
Cost
₱58M
Start
Apr 10, 2023
Completion
Dec 06, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
QM BUILDERS
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Revetment Wall at Brgy. Colabtingon, Dumanjug, Cebu

P00721509VS Completed
Location
Dumanjug, Cebu
Cost
₱96M
Start
Feb 07, 2023
Completion
Aug 22, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
QM BUILDERS
Tap to view details
Flood Control Infrastructure Main Portal

Construction of River Retaining Wall at Brgy. Kantangkas (Left Side), Dumanjug Cebu

P00721886VS Completed
Location
Kantangkas, Dumanjug, Cebu
Cost
₱96M
Start
Mar 22, 2023
Completion
Oct 10, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
QM BUILDERS
Tap to view details
Flood Control Infrastructure Main Portal

Construction of River Control Structure at Barangay Tubod-Dugoan (Upstream), Dumanjug, Cebu

P00733246VS Completed
Location
Tubod-Dugoan, Dumanjug, Cebu
Cost
₱87M
Start
Apr 10, 2023
Completion
Sep 24, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
QM BUILDERS
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Dike at Valencia River (Upstream Right Side), Alegria, Cebu

P00721878VS Completed
Location
Valencia, Alegria, Cebu
Cost
₱96M
Start
Mar 15, 2023
Completion
Jun 19, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
NEWBIG FOUR J CONSTRUCTION INC., (FORMERLY FOUR J
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Storm Surge Protection Strucures at Sitio Balhaan, Brgy. Looc, Ginatilan, Cebu (Package 1)

P00733276VS Completed
Location
Looc, Ginatilan, Cebu
Cost
₱92M
Start
Apr 10, 2023
Completion
Dec 10, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
QM BUILDERS
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Storm Surge Protection Structures at Sitio Lutak, Brgy. Guiwanon, Ginatilan, Cebu (Package 1)

P00733304VS Completed
Location
Guiwanon, Ginatilan, Cebu
Cost
₱49M
Start
Apr 10, 2023
Completion
Nov 12, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
QM BUILDERS
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Revetment Wall (Upstream) at Brgy. Tapon, Dumanjug, Cebu

P00721874VS Completed
Location
Tapon, Dumanjug, Cebu
Cost
₱96M
Start
Mar 22, 2023
Completion
Jan 29, 2024
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
QM BUILDERS
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Revetment Wall along Sitio Elithon, Barangay Vive River Flood Control, Ronda, Cebu

P00733239VS Completed
Location
Vive, Ronda, Cebu
Cost
₱96M
Start
Apr 10, 2023
Completion
Feb 18, 2024
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
WTG CONSTRUCTION & DEVELOPMENT CORPORATION
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Lagnason Flood Control, Oslob, Cebu

P00721675VS Completed
Location
Oslob, Cebu
Cost
₱29M
Start
Feb 09, 2023
Completion
May 14, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
EOZ CONSTRUCTION
Tap to view details
Flood Control Infrastructure Main Portal

Rehabilitation of Riverbank along Ylaya River, Purok Manga Section, Brgy. Ylaya (Left Side), Ronda, Cebu

P00733743VS Completed
Location
Ronda, Cebu
Cost
₱96M
Start
Apr 10, 2023
Completion
Jun 20, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
NEWBIG FOUR J CONSTRUCTION INC., (FORMERLY FOUR J
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Flood Mitigation Structure at Upstream and Downstream of Box Culvert at Tagbilaran North Rd (Tagbilaran-Jetafe Section) K0051+312, Tubigon, Bohol

P00721939VS Completed
Location
Tubigon, Bohol
Cost
₱9.8M
Start
May 11, 2023
Completion
Nov 16, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
3N CONSTRUCTION & SUPPLY
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Revetment Wall along Barangay Vive River Flood Control, Ronda, Cebu

P00733237VS Completed
Location
Vive, Ronda, Cebu
Cost
₱96M
Start
Apr 10, 2023
Completion
Feb 18, 2024
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
WTG CONSTRUCTION & DEVELOPMENT CORPORATION
Tap to view details

Data Source

Powered by official government infrastructure monitoring data

Project DIME

Digital Imaging for Monitoring and Evaluation

A digital transformation initiative by the Department of Budget and Management (DBM) in partnership with the Philippine Open Government Partnership, relaunched in 2023 to enable participatory and real-time monitoring of government infrastructure projects.

How It Works

Advanced Monitoring: Uses satellites, drones, and geotagging technologies to track high-value infrastructure projects nationwide

Citizen Participation: Empowers Filipinos to monitor project progress and provide feedback on actual project status

Enhanced Transparency: Ensures public funds are used effectively through open data and real-time project monitoring

Mission

Provide an efficient mechanism for monitoring and evaluation of government programs through innovative use of technologies

Vision

Integrate science-based monitoring and evaluation principles into the government's budget and management system

"Project DIME is a game-changer—ensuring greater efficiency, transparency, and public participation in the way services are delivered to the Filipino people."

Secretary Amenah F. Pangandaman

DBM Secretary

Learn more about Project DIME
Visit Official Site