Flood Control Infrastructure Main Portal

Construction of Drainage System and Sidewalk along Karuhatan Service Road NLEX (Phase II), Brgy. Karuhatan, Valenzuela City

P00740504LZ Completed
Location
City of Valenzuela
Cost
₱19M
Start
Jun 18, 2023
Completion
Apr 11, 2024
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
SONPRO CONSTRUCTION
Tap to view details
Flood Control Infrastructure Main Portal

Rehabilitation of Flood Mitigation Structure along San Juan River (Phase XIX), Quezon City

P00727035LZ Completed
Location
Quezon City
Cost
₱49M
Start
Mar 12, 2023
Completion
Nov 06, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
MRB11 CONSTRUCTION CORPORATION (FORMERLY:MRB CONS
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Flood Control Structure and Tributaries along Pasong Tamo Creek, Sta. 0+000 to Sta. 0+805 (Left Side), Quezon City

P00742247LZ Completed
Location
Quezon City
Cost
₱9.7M
Start
Mar 20, 2023
Completion
Jul 20, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
REND ENTERPRISES & GENERAL CONTRACTOR
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Babanse 1 Pumping Station, Brgy. NBBS Kaunlaran, Navotas City

P00726992LZ Completed
Location
City of Navotas
Cost
₱23M
Start
Mar 07, 2023
Completion
Dec 26, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
EARTHWORK BUILDERS, INC. (FORMERLY: EARTHWORK MOVERS)
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Flood Control Wall along Sitio Matarik Creek, Sta. 0 + 484 - Sta. 0 + 971, Caloocan City

P00735955LZ Completed
Location
Barangay 175, City of Caloocan
Cost
₱80M
Start
Feb 20, 2023
Completion
Dec 11, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
MRB11 CONSTRUCTION CORPORATION (FORMERLY:MRB CONS
Tap to view details
Flood Control Infrastructure Main Portal

Rehabilitation of Drainage, Pamplona 1, Las Piñas City (Phase II)

P00742215LZ Completed
Location
City of Las Piñas
Cost
₱4.9M
Start
Apr 16, 2023
Completion
Jul 29, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
OMNICON BUILDERS
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Slope Protection and Groundsill Structure along Villanueva Creek near Schilling Lane, Brgy. San Dionisio, Parañaque City

P00742111LZ Completed
Location
City of Parañaque
Cost
₱96M
Start
Jul 09, 2023
Completion
Dec 15, 2024
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
E.R. RODRIGUEZ CONSTRUCTION CORPORATION (FORMERLY: E.R. RODRIGUEZ CONSTRUCTION)
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Flood Control Wall along Lingunan Creek, Veinte Reales, Valenzuela City

P00726804LZ Completed
Location
City of Valenzuela
Cost
₱94M
Start
Apr 19, 2023
Completion
Jun 10, 2024
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
J. SIMEON CONSTRUCTION / MIGHTY CONSTRUCTION & DEVELOPMENT INC.
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Flood Control Wall along the Banks of Matarik Creek, Brgy. 175 (Phase 3), Caloocan City

P00725558LZ Completed
Location
Barangay 177, City of Caloocan
Cost
₱89M
Start
Feb 20, 2023
Completion
Dec 25, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
IM CONSTRUCTION CORPORATION
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Flood Control Structures at Brgy. Pasong Tamo, Quezon City

P00740507LZ Completed
Location
Quezon City
Cost
₱29M
Start
Mar 20, 2023
Completion
Nov 12, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
WAY MAKER GENERAL CONTRACTOR OPC
Tap to view details
Flood Control Infrastructure Main Portal

Rehabilitation of Flood Mitigation Structure along San Juan River, Quezon City (Phase XVII)

P00726032LZ Completed
Location
Quezon City
Cost
₱42M
Start
Feb 16, 2023
Completion
Nov 12, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
AKN CONSTRUCTION CORPORATION
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Drainage System along East Capitol Drive and Sta. Rosa St., and vicinity Kapitolyo, Pasig City

P00725952LZ Completed
Location
City of Pasig
Cost
₱5.1M
Start
Feb 05, 2023
Completion
Aug 05, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
816 EMBER CONSTRUCTION CORPORATION
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Retention Basin along Estero de Valencia (Phase V), Manila City

P00725508LZ Completed
Location
Barangay 9, City of Manila
Cost
₱88M
Start
Feb 22, 2023
Completion
Feb 19, 2024
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
SUPREME ABF CONST. & CONST. SUPPLY COMPANY INC. / RJR CALCON CORP.
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Box Culvert along Anonas St., Manila City

P00727025LZ Completed
Location
Barangay 55, City of Manila
Cost
₱44M
Start
Feb 28, 2023
Completion
Sep 29, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
G.F. FABIAN CONSTRUCTION
Tap to view details
Flood Control Infrastructure Main Portal

Rehabilitation of Flood Control Structure Along Ilang-Ilang Creek Leading to Tullahan River, Barangay Sta. Monica, Quezon City

P00726023LZ Completed
Location
Quezon City
Cost
₱48M
Start
Feb 12, 2023
Completion
Nov 26, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
MRB11 CONSTRUCTION CORPORATION (FORMERLY:MRB CONS / MANCOL CONSTRUCTION CORPORATION
Tap to view details
Flood Control Infrastructure Main Portal

Construction of Flood Control Wall along the Banks of Creeks, Brgy. 178, Caloocan City

P00727015LZ Completed
Location
City of Caloocan
Cost
₱24M
Start
May 18, 2023
Completion
Nov 26, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
CALCON ENGINEERING
Tap to view details
Flood Control Infrastructure Main Portal

Installation of Booster Pump along Estero dela Reina, Barangay 9, (Phase II), Tondo, Manila

P00725477LZ Completed
Location
City of Manila
Cost
₱94M
Start
Feb 15, 2023
Completion
Jul 24, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
EIGHT J'S CONSTRUCTION SERVICES
Tap to view details
Flood Control Infrastructure Main Portal

Installation of Booster Pump at Estero de Magdalena (Recto Section) (Phase I), Manila City

P00725504LZ Completed
Location
Barangay 18, City of Manila
Cost
₱85M
Start
Feb 16, 2023
Completion
Jul 15, 2023
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
AL-AMEN BUILDERS / ST. TIMOTHY CONSTRUCTION CORPORATION
Tap to view details
Flood Control Infrastructure Main Portal

Rehabilitation of Lagarian Creek, Quezon City

P00727029LZ Completed
Location
Quezon City
Cost
₱20M
Start
Mar 28, 2023
Completion
Mar 13, 2024
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
E.L. TORRES CONSTRUCTION AND TRADING INC. (FORMERLY : E. L. TORRES CONSTRUCTION & TRADING
Tap to view details
Flood Control Infrastructure Main Portal

Rehabilitation of Drainage System with Ground Improvement at Barangay 20, Tondo, Manila City

P00737400LZ Completed
Location
City of Manila
Cost
₱20M
Start
Feb 13, 2023
Completion
Sep 19, 2024
Fund Source
General Appropriations Act FY 2023
Agencies
DPWH
Contractor
JJPR CONSTRUCTION SERVICES
Tap to view details

Data Source

Powered by official government infrastructure monitoring data

Project DIME

Digital Imaging for Monitoring and Evaluation

A digital transformation initiative by the Department of Budget and Management (DBM) in partnership with the Philippine Open Government Partnership, relaunched in 2023 to enable participatory and real-time monitoring of government infrastructure projects.

How It Works

Advanced Monitoring: Uses satellites, drones, and geotagging technologies to track high-value infrastructure projects nationwide

Citizen Participation: Empowers Filipinos to monitor project progress and provide feedback on actual project status

Enhanced Transparency: Ensures public funds are used effectively through open data and real-time project monitoring

Mission

Provide an efficient mechanism for monitoring and evaluation of government programs through innovative use of technologies

Vision

Integrate science-based monitoring and evaluation principles into the government's budget and management system

"Project DIME is a game-changer—ensuring greater efficiency, transparency, and public participation in the way services are delivered to the Filipino people."

Secretary Amenah F. Pangandaman

DBM Secretary

Learn more about Project DIME