Construction of Malbog River Flood Mitigation Structure, Barangay Mayon, Castilla, Sorsogon
Location
Mayon, Castilla, Sorsogon
Bicol Region
ZIP: 4713
12.952611, 123.776386
Project Cost
₱120M
₱117,298,238.6
Project Timeline
Start Date
February 20, 2024
Tue, Feb 20, 2024
Actual Start
February 20, 2024
Tue, Feb 20, 2024
Target Completion
November 10, 2024
Sun, Nov 10, 2024
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor