Construction of Flood Mitigation structure along Sagñay River Brgy. del Carmen, Sagñay, Camarines Sur
Location
San Jose, Camarines Sur
Bicol Region
ZIP: 4422
13.593920, 123.525170
Project Cost
₱67M
₱66,875,340.0
Project Timeline
Start Date
May 14, 2023
Sun, May 14, 2023
Actual Start
May 14, 2023
Sun, May 14, 2023
Target Completion
March 04, 2024
Mon, Mar 04, 2024
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor