Construction of Sto. Cristo Seawall (Phase 3), Tabaco City, Albay
Location
City of Tabaco, Albay
Bicol Region
ZIP: 4511
13.213027, 123.446610
Project Cost
₱42M
₱41,650,000.0
Project Timeline
Start Date
June 25, 2023
Sun, Jun 25, 2023
Actual Start
June 25, 2023
Sun, Jun 25, 2023
Target Completion
February 13, 2024
Tue, Feb 13, 2024
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor