Construction of Bank Protection Structure along Bicol River, Palsong-Sto. Domingo Section, Bula, Camarines Sur
Location
Palsong, Bula, Camarines Sur
Bicol Region
ZIP: 4430
13.421148, 123.311704
Project Cost
₱96M
₱96,314,191.85
Project Timeline
Start Date
February 16, 2023
Thu, Feb 16, 2023
Actual Start
February 16, 2023
Thu, Feb 16, 2023
Target Completion
December 06, 2023
Wed, Dec 06, 2023
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor