Construction of Bank Protection Structure along Pawili River, Brgy. Salvacion-San Roque Section, Bula, Camarines Sur
Location
Bula, Camarines Sur
Bicol Region
ZIP: 4430
13.460260, 123.268090
Project Cost
₱68M
₱67,539,164.0
Project Timeline
Start Date
February 16, 2023
Thu, Feb 16, 2023
Actual Start
February 16, 2023
Thu, Feb 16, 2023
Target Completion
August 17, 2023
Thu, Aug 17, 2023
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates