Construction of Bank Protection Structure along Bicol River, San Roque Section, Bula, Camarines Sur
Location
Bula, Camarines Sur
Bicol Region
ZIP: 4430
13.458554, 123.267524
Project Cost
₱96M
₱96,456,652.25
Project Timeline
Start Date
February 16, 2023
Thu, Feb 16, 2023
Actual Start
February 16, 2023
Thu, Feb 16, 2023
Target Completion
July 23, 2023
Sun, Jul 23, 2023
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close
Loading comments...