Construction of Riverbank Protection Structure along Libmanan River, Brgy. Tapi Section, Lupi, Camarines Sur
Location
Tapi, Lupi, Camarines Sur
Bicol Region
ZIP: 4402
13.784558, 122.926236
Project Cost
₱81M
₱80,966,304.71
Project Timeline
Start Date
March 30, 2023
Thu, Mar 30, 2023
Actual Start
March 30, 2023
Thu, Mar 30, 2023
Target Completion
January 07, 2024
Sun, Jan 07, 2024
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project