Construction of Drainage System at Purok 5, Ledesma Subd., Barangay 10-A, Davao City
Location
City of Davao, Davao Del Sur
Davao Region
ZIP: 8000
7.084805, 125.604656
Project Cost
₱6.9M
₱6,860,000.0
Project Timeline
Start Date
April 12, 2022
Tue, Apr 12, 2022
Actual Start
April 12, 2022
Tue, Apr 12, 2022
Target Completion
August 23, 2022
Tue, Aug 23, 2022
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates