Construction of Revetment along Manat River leading to Agusan River at Inambatan Bridge (Downstream), Brgy. Olaycon, Monkayo, Davao de Oro
Location
Olaycon, Monkayo, Davao De Oro
Davao Region
ZIP: 8805
7.797090, 126.037198
Project Cost
₱68M
₱67,549,964.47
Project Timeline
Start Date
February 22, 2022
Tue, Feb 22, 2022
Actual Start
February 22, 2022
Tue, Feb 22, 2022
Target Completion
November 17, 2022
Thu, Nov 17, 2022
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close