Construction of Flood Control Structure along Saug River, Protecting Tagum-Panabo Circumferential Road, Asuncion, Davao del Norte
Location
New Santiago, Asuncion, Davao Del Norte
Davao Region
ZIP: 8102
7.539431, 125.756547
Project Cost
₱58M
₱57,882,638.53
Project Timeline
Start Date
February 28, 2022
Mon, Feb 28, 2022
Actual Start
February 28, 2022
Mon, Feb 28, 2022
Target Completion
March 11, 2023
Sat, Mar 11, 2023
Project Location Map
Location Map
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates