Construction of Flood Control Structure along Hijo River, Brgy. Madaum, Tagum City, Davao del Norte
Location
Madaum, City of Tagum, Davao Del Norte
Davao Region
ZIP: 8100
7.365850, 125.834269
Project Cost
₱150M
₱148,499,998.4
Project Timeline
Start Date
April 01, 2024
Mon, Apr 01, 2024
Actual Start
April 01, 2024
Mon, Apr 01, 2024
Target Completion
December 03, 2024
Tue, Dec 03, 2024
Project Location Map
Location Map
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close