Construction of Concrete Revetment along Talomo River, Balite Section, Sta. 0 + 000 - Sta. 0 + 500, Davao City
Location
City of Davao, Davao Del Sur
Davao Region
ZIP: 8000
7.176266, 125.462135
Project Cost
₱48M
₱47,696,875.08
Project Timeline
Start Date
March 08, 2023
Wed, Mar 08, 2023
Actual Start
March 08, 2023
Wed, Mar 08, 2023
Target Completion
August 20, 2023
Sun, Aug 20, 2023
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor