Construction of Revetment along Matina River, Matina Pangi Bridge II Downstream, Both Banks, Davao City
Location
Matina Pangi, City of Davao, Davao Del Sur
Davao Region
ZIP: 8000
7.067658, 125.569844
Project Cost
₱190M
₱188,175,000.0
Project Timeline
Start Date
August 13, 2023
Sun, Aug 13, 2023
Actual Start
August 13, 2023
Sun, Aug 13, 2023
Target Completion
September 29, 2024
Sun, Sep 29, 2024
Project Location Map
Location Map
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor