Construction of Revetment along Matina River, Outfall Section, Sta. 0+465 to Sta. 0+790, Left Bank, Davao City
Location
Matina Crossing, City of Davao, Davao Del Sur
Davao Region
ZIP: 8000
7.048640, 125.564130
Project Cost
₱94M
₱94,273,146.01
Project Timeline
Start Date
November 30, 2021
Tue, Nov 30, 2021
Actual Start
November 30, 2021
Tue, Nov 30, 2021
Target Completion
August 30, 2024
Fri, Aug 30, 2024
Project Location Map
Location Map
Source of Fund
1 source
General Appropriations Act FY 2021
Implementing Agency
1 agency
Contractor
1 contractor