Construction of Revetment along Talomo River, Sta. 0+000 - Sta. 0+213, Sta. 0+405 - Sta. 0+460,Left Bank, Davao City
Location
City of Davao, Davao Del Sur
Davao Region
ZIP: 8000
7.046261, 125.561111
Project Cost
₱97M
₱96,500,000.0
Project Timeline
Start Date
November 30, 2021
Tue, Nov 30, 2021
Actual Start
November 30, 2021
Tue, Nov 30, 2021
Target Completion
April 14, 2023
Fri, Apr 14, 2023
Source of Fund
1 source
General Appropriations Act FY 2021
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close