Flood Control Infrastructure
Main Portal
Completed
Construction of Revetment along Talomo River, NHA Bangkal Section, Sta. 0+180 - Sta. 0+405, Left Bank, Davao City
P00522308MN
Location
City of Davao, Davao Del Sur
Davao Region
ZIP: 8000
7.046644, 125.561735
Project Cost
₱97M
₱96,500,000.0
Project Timeline
Start Date
November 30, 2021
Tue, Nov 30, 2021
Actual Start
November 30, 2021
Tue, Nov 30, 2021
Target Completion
March 19, 2023
Sun, Mar 19, 2023
Project Organizations
Source of Fund
1 source
General Appropriations Act FY 2021
Implementing Agency
1 agency
DPWH
Project Updates
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project