Construction of Slope Protection Structure, Phase 3B - Carissa 3-A, Brgy. Kaypian, City of San Jose del Monte, Bulacan
Location
Kaypian, City of San Jose Del Monte, Bulacan
Central Luzon
ZIP: 3023
14.829120, 121.057490
Project Cost
₱49M
₱48,997,036.71
Project Timeline
Start Date
May 25, 2022
Wed, May 25, 2022
Actual Start
May 25, 2022
Wed, May 25, 2022
Target Completion
January 01, 2023
Sun, Jan 01, 2023
Project Location Map
Location Map
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor