Improvement of Waterway along Bulo River, Sta. 01 + 880 - Sta. 02 + 320 (Left Side), San Miguel, Bulacan
Location
Poblacion, San Miguel, Bulacan
Central Luzon
ZIP: 3011
15.169260, 120.937800
Project Cost
₱49M
₱48,995,909.06
Project Timeline
Start Date
March 29, 2022
Tue, Mar 29, 2022
Actual Start
March 29, 2022
Tue, Mar 29, 2022
Target Completion
October 14, 2022
Fri, Oct 14, 2022
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates