Construction of Slope Protection, Brgy. Gumaok East - Central, City of San Jose del Monte, Bulacan
Location
City of San Jose Del Monte, Bulacan
Central Luzon
ZIP: 3023
14.797920, 121.065320
Project Cost
₱96M
₱96,471,127.99
Project Timeline
Start Date
May 25, 2022
Wed, May 25, 2022
Actual Start
May 25, 2022
Wed, May 25, 2022
Target Completion
May 17, 2023
Wed, May 17, 2023
Project Location Map
Location Map
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close
Loading comments...