Construction of Malabbaga Flood Control Structure (Phase III), Sta. 6 + 820 - Sta. 7 + 820, La Paz, Abra
Location
Malabbaga, La Paz, Abra
CAR
ZIP: 2826
17.690574, 120.705820
Project Cost
₱92M
₱91,539,920.3
Project Timeline
Start Date
February 14, 2023
Tue, Feb 14, 2023
Actual Start
February 14, 2023
Tue, Feb 14, 2023
Target Completion
July 13, 2023
Thu, Jul 13, 2023
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close
Loading comments...