Flood Control Infrastructure
Main Portal
Completed
Construction of Malanas Flood Control Structure, Guimba and Daoidao, San Juan, Abra
P00639325LZ
Location
Guimba, San Juan, Abra
CAR
ZIP: 2825
17.679863, 120.730362
Project Cost
₱96M
₱96,495,674.0
Project Timeline
Start Date
May 25, 2022
Wed, May 25, 2022
Actual Start
May 25, 2022
Wed, May 25, 2022
Target Completion
August 22, 2022
Mon, Aug 22, 2022
Project Organizations
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
DPWH