Construction of Mataliling Flood Control Structure, Sta. 181+310 - Sta. 181+410 (L.S.), Upper Uma, Lubuagan, Kalinga
Location
Upper Uma, Lubuagan, Kalinga
CAR
ZIP: 3802
17.354920, 121.150330
Project Cost
₱4.5M
₱4,467,751.53
Project Timeline
Start Date
April 05, 2022
Tue, Apr 05, 2022
Actual Start
April 05, 2022
Tue, Apr 05, 2022
Target Completion
September 22, 2022
Thu, Sep 22, 2022
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates