Construction of Flood Control Structure, Malabbaga, La Paz, Abra
Location
Malabbaga, La Paz, Abra
CAR
ZIP: 2826
17.688349, 120.705578
Project Cost
₱91M
₱91,407,703.9
Project Timeline
Start Date
February 14, 2023
Tue, Feb 14, 2023
Actual Start
February 14, 2023
Tue, Feb 14, 2023
Target Completion
November 16, 2023
Thu, Nov 16, 2023
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor