Construction of Flood Mitigation Structure within Agno River Basin: along Agno River Section 20 (Ekip), Bokod, Benguet
Location
Ekip, Bokod, Benguet
CAR
ZIP: 2605
16.523554, 120.875651
Project Cost
₱24M
₱23,765,066.8
Project Timeline
Start Date
May 09, 2022
Mon, May 09, 2022
Actual Start
May 09, 2022
Mon, May 09, 2022
Target Completion
November 10, 2022
Thu, Nov 10, 2022
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates