Construction of Open Canal Brgy Rantian Ditsaan-Ramain Lanao Del Sur
Location
Rantian, Ditsaan-Ramain, Lanao Del Sur
BARMM
ZIP: 9712
7.970865, 124.352569
Project Cost
₱9.6M
₱9,602,479.28
Project Timeline
Start Date
August 07, 2022
Sun, Aug 07, 2022
Actual Start
August 07, 2022
Sun, Aug 07, 2022
Target Completion
January 08, 2023
Sun, Jan 08, 2023
Project Location Map
Location Map
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor