Construction of Flood Mitigation Structure along Laoag River Basin, Dingris River, Left Bank, barangay Maruaya, Piddig, Ilocos Norte
Location
Piddig, Ilocos Norte
Ilocos Region
ZIP: 2915
18.197450, 120.747830
Project Cost
₱97M
₱97,464,756.1
Project Timeline
Start Date
February 13, 2023
Mon, Feb 13, 2023
Actual Start
February 13, 2023
Mon, Feb 13, 2023
Target Completion
December 11, 2023
Mon, Dec 11, 2023
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project