Construction of Flood Control Structure along Baag River Left Bank, Sitio Mabiga East, Brgy. Pasaleng, Pagudpud, Ilocos Norte
Location
Pasaleng, Pagudpud, Ilocos Norte
Ilocos Region
ZIP: 2919
18.550600, 120.946383
Project Cost
₱58M
₱57,899,669.4
Project Timeline
Start Date
March 12, 2023
Sun, Mar 12, 2023
Actual Start
March 12, 2023
Sun, Mar 12, 2023
Target Completion
August 17, 2023
Thu, Aug 17, 2023
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project