Construction of Retaining Wall at Candon City Sports and Convention Center, Candon City, Ilocos Sur
Location
City of Candon, Ilocos Sur
Ilocos Region
ZIP: 2710
17.203588, 120.458571
Project Cost
₱29M
₱28,517,340.1
Project Timeline
Start Date
May 18, 2022
Wed, May 18, 2022
Actual Start
May 18, 2022
Wed, May 18, 2022
Target Completion
September 19, 2023
Tue, Sep 19, 2023
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor