Construction of Flood Control Structure along Bauang River, Downstream of Bauang Bridge 1, Brgys. Parian Este - Nagrebcan, Bauang, La Union
Location
Parian Este, Bauang, La Union
Ilocos Region
ZIP: 2501
16.519011, 120.329084
Project Cost
₱77M
₱77,199,690.4
Project Timeline
Start Date
March 02, 2023
Thu, Mar 02, 2023
Actual Start
March 02, 2023
Thu, Mar 02, 2023
Target Completion
March 31, 2024
Sun, Mar 31, 2024
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor