Construction of Flood Control Structure along the Aringay River Basin, Tubao, La Union (Package 3)
Location
Tubao, La Union
Ilocos Region
ZIP: 2509
16.372723, 120.404870
Project Cost
₱72M
₱72,334,993.6
Project Timeline
Start Date
April 18, 2023
Tue, Apr 18, 2023
Actual Start
April 18, 2023
Tue, Apr 18, 2023
Target Completion
February 10, 2024
Sat, Feb 10, 2024
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project