Construction of Flood Control Structure along Padsan River, Barangay 21 San Marcos, Sarrat, Ilocos Norte (Phase 2)
Location
San Marcos, Sarrat, Ilocos Norte
Ilocos Region
ZIP: 2914
18.148655, 120.674277
Project Cost
₱49M
₱48,999,571.3
Project Timeline
Start Date
February 26, 2024
Mon, Feb 26, 2024
Actual Start
February 26, 2024
Mon, Feb 26, 2024
Target Completion
September 23, 2024
Mon, Sep 23, 2024
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project