Construction of Flood Control Structure, Barangay Langcuas, San Fernando City, La Union
Location
Langcuas, City of San Fernando, La Union
Ilocos Region
ZIP: 2500
16.614697, 120.342305
Project Cost
₱39M
₱38,599,971.4
Project Timeline
Start Date
March 10, 2024
Sun, Mar 10, 2024
Actual Start
March 10, 2024
Sun, Mar 10, 2024
Target Completion
November 14, 2024
Thu, Nov 14, 2024
Project Location Map
Location Map
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor