Construction of Flood Control Structure along Aringay River Basin, Barangay Sto. Rosario West, Aringay, La Union
Location
Aringay, La Union
Ilocos Region
ZIP: 2503
16.388885, 120.333738
Project Cost
₱96M
₱96,479,841.9
Project Timeline
Start Date
March 07, 2024
Thu, Mar 07, 2024
Actual Start
March 07, 2024
Thu, Mar 07, 2024
Target Completion
January 19, 2025
Sun, Jan 19, 2025
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor