Construction of Flood Control Structure along Aringay River, Barangay San Juan West, Aringay, La Union
Location
San Juan West, Aringay, La Union
Ilocos Region
ZIP: 2503
16.407500, 120.381000
Project Cost
₱140M
₱144,749,933.0
Project Timeline
Start Date
May 02, 2024
Thu, May 02, 2024
Actual Start
May 02, 2024
Thu, May 02, 2024
Target Completion
August 09, 2024
Fri, Aug 09, 2024
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor