Construction (Completion) of River Control Structure and Drainage System, Bangon River Control, Tablas Island, Romblon
Location
Odiongan, Romblon
MIMAROPA Region
12.386336, 121.980937
Project Cost
₱110M
₱106,147,622.3
Project Timeline
Start Date
May 23, 2022
Mon, May 23, 2022
Actual Start
May 23, 2022
Mon, May 23, 2022
Target Completion
June 06, 2023
Tue, Jun 06, 2023
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet