Construction of Anahawin Flood Control Structure (Poypoy East and West Section), Sta. 0 + 000 - Sta. 0 + 682, Calintaan, Occidental Mindoro
Location
Poypoy, Calintaan, Occidental Mindoro
MIMAROPA Region
ZIP: 5104
12.622526, 121.005390
Project Cost
₱45M
₱44,848,347.79
Project Timeline
Start Date
February 09, 2023
Thu, Feb 09, 2023
Actual Start
February 09, 2023
Thu, Feb 09, 2023
Target Completion
July 14, 2023
Fri, Jul 14, 2023