Construction of Patrick Flood Control (Kambingan Section), Sta. 0+000 - Sta. 0+070 (RS), Sta. 0+140 - Sta. 0+477.25 (RS), Sablayan, Occidental Mindoro
Location
Sablayan, Occidental Mindoro
MIMAROPA Region
ZIP: 5104
12.926667, 120.816942
Project Cost
₱48M
₱48,249,953.59
Project Timeline
Start Date
July 05, 2022
Tue, Jul 05, 2022
Actual Start
July 05, 2022
Tue, Jul 05, 2022
Target Completion
July 02, 2023
Sun, Jul 02, 2023
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close
Loading comments...