Construction of Mansalay River Control at Brgy. Teresita, Mansalay, Oriental Mindoro
Location
Mansalay, Oriental Mindoro
MIMAROPA Region
ZIP: 5213
12.532222, 121.428611
Project Cost
₱9.9M
₱9,897,188.49
Project Timeline
Start Date
March 23, 2023
Thu, Mar 23, 2023
Actual Start
March 23, 2023
Thu, Mar 23, 2023
Target Completion
May 21, 2023
Sun, May 21, 2023
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close
Loading comments...