Construction of CSR Drainage Canal K0042 + 066 - K0042 + 471
Location
Victoria, Oriental Mindoro
MIMAROPA Region
13.126848, 121.290262
Project Cost
₱4.6M
₱4,604,034.99
Project Timeline
Start Date
March 29, 2023
Wed, Mar 29, 2023
Actual Start
March 29, 2023
Wed, Mar 29, 2023
Target Completion
June 26, 2023
Mon, Jun 26, 2023
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project