Construction of Labangan Bridge I Flood Control Structure, Sta. 0 + 000 - Sta. 0 + 229.02, Coron, Palawan
Location
Coron, Palawan
MIMAROPA Region
ZIP: 5316
12.047626, 120.155234
Project Cost
₱20M
₱20,088,519.55
Project Timeline
Start Date
May 30, 2023
Tue, May 30, 2023
Actual Start
May 30, 2023
Tue, May 30, 2023
Target Completion
September 30, 2024
Mon, Sep 30, 2024
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor